We now have 140 commitments totaling $3.248 Million + and we received almost $1.625 million! Thank you for your continued support!
Shall we say “Let there be light”!
With state-of-the-art Audio Visual System including high performance audio best-in-class pickup and reduced noise hearing assistance with easy to wear neck loop for listeners with T-coil equipped hearing aids!
Supported by ultimate high strength steel re-enforcing our roof structure!
with concrete and more concrete – Our new patio is coming!
Coming Soon!
Excellent progress is being made in the Activity Center/Gym construction. The patio has been formed and is ready for concrete pouring next week.
The Activity Center ceiling vinyl insulation has been repaired, sealed and painted. Our new state of the art light low energy fixtures with dimming controls along with Bose array speakers are being installed. Walls are being painted.
We are getting close to installing the Glass Windows and Doors, preparing the floor for installation and moving in mid to end June!
Thank you for your continued support!
As of 5-18-18 we have 139 commitments totaling 3.248 million + and we received $1,577,641.00!
Thank you for your continued support!